Republic of Ghana · Environmental Protection AuthorityPublished data snapshot · 23 July 2026

Ghana NDC evidence portal

PoA21 · National utility-scale solar PV acceleration programme

Establishment and operation of large grid-connected solar PV plants to displace fossil-fuel based grid electricity and improve renewable electricity supply.

Programme record

Policy Action
PA8 · Scale up new renewable energ penetration by 10% by 2030
Sector / objective
Energy · Mitigation
Thematic area
Energy transition
Technology
Utility-scale grid-connected solar PV
Indicator
Utility-scale solar PV installed (MW)
2025 baseline
133.10
2030 target
902.00
2035 target
1,200.00
Investment requirement
US$1,957.52 million
ERP
1,146.52 ktCO₂e